[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117298,789,1,"单选题","土石方工程采用混合单价方法计价，其中土方工程实行总价包干，包干价20 万元，石方工程实行单价合同，该工程有关的工程量和价格资料如下表所示。则该工程的结算价款是（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","87.2",false,{"key":16,"text":17,"correct":14},"B","88.2",{"key":19,"text":20,"correct":21},"C","92.0",true,{"key":23,"text":24,"correct":14},"D","93.0","总价包干20万。单价合同以实际工程量为准，3000*240，结算价为20+72=92万元",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]