[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117297":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117297,789,1,"单选题","下列合同履约情形中，属于发包人违约的情形是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理人无正当理由未在约定期限内发出复工指示，导致承包人无法复工的",true,{"key":16,"text":17,"correct":18},"B","因地震造成工程停工的",false,{"key":20,"text":21,"correct":18},"C","发包人支付合同进度款后，承包人未及时发放给民工的",{"key":23,"text":24,"correct":18},"D","发包人提供的测量资料错误导致承包人工程返工的","本题考查的是发包人的责任与义务。选项B属于不可抗力原因，并不是发包人原因。选项C属于承包人的原因。选项D属于发包人的责任，发包人义务中并没有包含选项D。相比较的话，选项A更符合题意。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]