[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117296":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":23},1117296,789,1,"单选题","建筑材料采购合同条款的相关说法，正确的是（ ）。 A.不属于国家定价的材料（产品），有供方确定价格 B.需方提货的，交货日期以需方收货戳记的日期为准 C.建筑材料的包装物由供方负责，并且一般不另向需方收费 D.建筑材料采购合同通常采用固定总价合同",[11,14,16,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","合同价款的支付一般分三次： （1）设备制造前，采购方支付设备价格的10%作为预付款； （2）供货方按照交货顺序在规定的时间内将货物送达交货地点，采购方支付该批设备价的80%； （3）剩余的10%作为设备保证金，待保证期满，采购方签发最终验收证书后支付。",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]