[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117292":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":23},1117292,789,1,"单选题","某工程因施工需要，需取得出入施工场地的临时道路的通行权，根据《标准施工招标文件》。该通行权应当由（ ）。 A.承包人负责办理，并承担有关费用 B.承包人负责办理，发包人承担有关费用 C.发包人负责办理，发包人承担有关费用 D.发包人负责办理，承包人承担有关费用",[11,14,16,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]