[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117288":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":23},1117288,789,1,"单选题","根据《建设工程施工专业分包合同》（GF-2003-0213），下列说法正确的是（ ）。 A.发包人向分包人提供具备施工条件的施工场地 B.分包人可直接致函发包人或工程师 C.就分包范围内的有关工作，承包人随时可以向分包人发出指令 D.分包合同价与总承包合同相应部分的价款存在连带关系",[11,14,16,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]