[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117285":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":15,"analysis":23},1117285,789,1,"单选题","根据九部委《标准施工招标文件》，监理人对隐蔽工程重新检查，经经验证明工程质量符合合同要求的，发包人应补偿承包人（ ）。 A.工期和费用 B.工期、费用和利润 C.费用和利润 D.工期和利润",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]