[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117284":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":23},1117284,789,1,"单选题","根据《标准施工招标文件》，关于暂停施工的说法，正确的是（ ）。 A.由于发包人原因引起的暂停施工，承包人有权要求延长工期和（或）增加费用，但不得要求补偿利润 B.发包人原因造成暂停施工，承包恩可不负责暂停施工期间工程的保护 C.因发包人原因发生暂停施工的紧急情况时，承包人可以先暂停施工，并及时向监理人提出暂停施工的书面请求 D.施工中出现一些意外需要暂停施工的，所有责任由发包人承担",[11,14,16,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",true,{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","由于发包人原因引起的暂停施工造成工期延误的，承包人有权要求发包人延长工期和（或）增加费用，并支付合理利润。 不论由于何种原因引起的暂停施工，暂停施工期间承包人应负责妥善保护工程并提供安全保障。",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]