[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117283":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":23},1117283,789,1,"单选题","某建设工程采用固定总价方式招标，业主在招标过程中对某项争议工程量不予更正，投标单位正确的应对策略是（ ）。 A.投标时注明工程量存在错误，应按实结算 B.修改工程量后进行报价 C.按业主要求工程量修改单价后报价 D.采用不平衡报价法提供该项工程报价",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",true,{"key":15,"text":15,"correct":16},"B",false,{"key":18,"text":18,"correct":16},"C",{"key":20,"text":20,"correct":16},"D",{"key":22,"text":22,"correct":16},"E","",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]