[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117281":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":15,"analysis":23},1117281,789,1,"单选题","在施工总承包管理模式下，项目总进度计划的编制、控制和协调，以及设计、施工、供货之间的进度计划协调由（ ）负责。 A.监理工程师 B.业主 C.施工总承包单位 D.施工总承包管理单位",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","施工总进度计划的编制、控制和协调由施工总承包管理单位负责，而项目总进度计划的编制、控制和协调，以及设计、施工、供货之间的进度计划协调由业主负责。",{"id":6,"name":25,"category":26,"favorite":27},"二建建设工程施工管理","建筑工程",0]