[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117235,789,1,"单选题","建设工程施工过程中对分部工程质量验收时，应该给出综合质量评价的检查项目是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分项工程质量验收",false,{"key":16,"text":17,"correct":14},"B","质量控制资料验收",{"key":19,"text":20,"correct":14},"C","主体结构功能检测",{"key":22,"text":23,"correct":24},"D","观感质量验收",true,"本题考查的是施工过程的工程质量验收。由于各分项工程的性质不尽相同，因此分部工程不能简单地将各分项工程组合进行验收，尚须增加以下两类检查项目：(1)涉及安全和使用功能的地基基础、主体结构及有关安全及重要使用功能的安装分部工程应进行有关见证取样送样试验或抽样检测;(2)观感质量验收。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]