[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117228":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117228,789,1,"单选题","施工质量检查中工序交接检查的“三检”制度是指（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","质量员检查，技术负责人检查，项目经理检查",false,{"key":16,"text":17,"correct":14},"B","施工单位检查，监理单位检查，建设单位检查",{"key":19,"text":20,"correct":21},"C","自检，互检，专检",true,{"key":23,"text":24,"correct":14},"D","施工单位内部检查，监理单位检查，建设单位检查","工序交接检查：对于重要的工序或对工程质量有重大影响的工序，应严格执行“三检”制度，即自检、互检、专检。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]