[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117225":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117225,789,1,"单选题","下列施工准备质量控制的工作中，属于技术准备的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","复核原始坐标",false,{"key":16,"text":17,"correct":14},"B","规划施工场地",{"key":19,"text":20,"correct":21},"C","设置质量控制点",true,{"key":23,"text":24,"correct":14},"D","布置施工机械","技术准备是指在正式开展施工作业活动前进行的技术准备工作。这类工作内容繁多，主要在室内进行。制定施工质量控制计划，设置质量控制点，明确关键部位的质量管理点。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]