[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117223":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117223,789,1,"单选题","在建设工程施工过程的质量验收中，检验批的合格质量主要取决于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","主控项目的检验结果",false,{"key":16,"text":17,"correct":14},"B","资料检查完整、合格和主控项目检验结果",{"key":19,"text":20,"correct":21},"C","主控项目和一般项目的检验结果",true,{"key":23,"text":24,"correct":14},"D","资料检查完整、合格和一般项目的检验结果","检验批的合格质量主要取决于对主控项目和一般项目的检验结果。主控项目是对检验批的基本质量起决定性影响的检验项目，因此，必须全部符合有关专业工程验收规范的规定。这意味着主控项目不允许有不符合要求的检验结果，这种项目的检查具有“否决权”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]