[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117217":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117217,789,1,"单选题","关于项目施工质量目标的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目施工质量总目标应符合行业质量最高目标要求",false,{"key":16,"text":17,"correct":14},"B","项目施工质量总目标要以相关标准规范为基本依据",{"key":19,"text":20,"correct":14},"C","项目施工质量总目标的分解仅需从空间角度立体展开",{"key":22,"text":23,"correct":24},"D","项目施工质量总目标应逐级分解以形成在合同环境下的各级质量目标",true,"要以工程承包合同为基本依据，逐级分解目标以形成在合同环境下的各级质量目标。项目施工质量目标的分解主要从两个角度展开，即：从时间角度展开，实施全过程控制；从空间角度展开，实现全方位和全员的质量目标管理。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]