[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117216":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117216,789,1,"单选题","质量管理的PDCA 循环中，“D”的职能包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定质量管理方针",false,{"key":16,"text":17,"correct":18},"B","对计划行动方案的交底和落实",true,{"key":20,"text":21,"correct":14},"C","检查是否严格执行了计划方案",{"key":23,"text":24,"correct":14},"D","纠偏和预防","实施包含两个环节，即计划行动方案的交底和按计划规定的方法及要求展开的施工作业技术活动。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]