[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117215":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117215,789,1,"单选题","建设工程施工质量保证体系运行的主线是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量计划",true,{"key":16,"text":17,"correct":18},"B","过程管理",false,{"key":20,"text":21,"correct":18},"C","PDCA 循环",{"key":23,"text":24,"correct":18},"D","质量手册","施工质量保证体系的运行，应以质量计划为主线，以过程管理为重心，按照PDCA 循环的原理。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]