[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117205":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117205,789,1,"单选题","下列建设工程施工方进度控制的措施中，属于技术措施的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","重视信息技术在进度控制中的作用",false,{"key":16,"text":17,"correct":14},"B","采用网络计划方法编制进度计划",{"key":19,"text":20,"correct":21},"C","分析工程设计变更的必要性和可能性",true,{"key":23,"text":24,"correct":14},"D","编制与进度相适应的资源需求计划","",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]