[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117204":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117204,789,1,"单选题","下列施工方进度控制的措施中，属于组织措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","优化工程施工方案",false,{"key":16,"text":17,"correct":18},"B","制定进度控制工作流程",true,{"key":20,"text":21,"correct":14},"C","应用BIM 信息模型",{"key":23,"text":24,"correct":14},"D","采用网络计划技术","施工方进度控制的组织措施如下。 （1）应充分重视健全项目管理的组织体系。 （2）在项目组织结构中应有专门的工作部门和符合进度控制岗位资格的专人负责进度控制工作。 （4）应编制施工进度控制的工作流程。 （5）应进行有关进度控制会议的组织设计。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]