[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117200":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117200,789,1,"单选题","某单代号网络计划如下图所示（时间单位：天），工作5 的最迟完成时间是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":18},"B","9",true,{"key":20,"text":21,"correct":14},"C","8",{"key":23,"text":24,"correct":14},"D","7","@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]