[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117199,789,1,"单选题","单代号网络计划时间参数计算中，相邻两项工作之间的时间间隔（LAGi-j）（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","紧后工作最早开始时间和本工作最早开始时间之差",false,{"key":16,"text":17,"correct":14},"B","紧后工作最早完成时间和本工作最早开始时间之差",{"key":19,"text":20,"correct":21},"C","紧后工作最早开始时间和本工作最早完成时间之差",true,{"key":23,"text":24,"correct":14},"D","紧后工作最迟完成时间和本工作最早完成时间之差","",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]