[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117198":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117198,789,1,"单选题","某工程的单代号网络计划如下图所示（时间单位：天），该计划的计算工期为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","9",false,{"key":16,"text":17,"correct":14},"B","11",{"key":19,"text":20,"correct":21},"C","12",true,{"key":23,"text":24,"correct":14},"D","15","",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]