[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117197":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117197,789,1,"单选题","双代号网络计划中的关键线路是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总时差为零的线路",false,{"key":16,"text":17,"correct":14},"B","总的工作持续时间最短的线路",{"key":19,"text":20,"correct":14},"C","一经确定，不会发生转移的线路",{"key":22,"text":23,"correct":24},"D","自始至终全部由关键工作组成的线路",true,"",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]