[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117194":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117194,789,1,"单选题","某网络计划中，已知工作M 的持续时间为6 天，总时差和自由时差分别为3 天和1 天；检查中发现该工作实际持续时间为9 天，则其对工程的影响是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","既不影响总工期，也不影响其紧后工作的正常进行",false,{"key":16,"text":17,"correct":14},"B","使其紧后工作的最迟开始时间推迟3 天，并使总工期延长1 天",{"key":19,"text":20,"correct":14},"C","使其紧后工作的最早开始时间推迟1 天，并使总工期延长3 天",{"key":22,"text":23,"correct":24},"D","不影响总工期，但使其紧后工作的最早开始时间推迟2 天",true,"",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]