[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117192":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":22},1117192,789,1,"单选题","某双代号网络计划如下图所示(时间：天)，则工作D 的自由时差是（ ）天。",[11,15,19],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","1","工作D 的最早开始时间为8，最早完成时间为10，工作C 的最早完成时间为12，工作F 的最早开始时间为12，所以D 工作的自由时差为其紧后工作的最早开始时间减去本身的最早完成时间=12-10=2。",{"id":6,"name":24,"category":25,"favorite":26},"二建建设工程施工管理","建筑工程",0]