[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117191":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117191,789,1,"单选题","关于横道图进度计划的说法，正确的时（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","横道图的一行只能表达一项工作",false,{"key":16,"text":17,"correct":14},"B","工作的简要说明必须放在表头内",{"key":19,"text":20,"correct":14},"C","横道图不能表达工作间的逻辑关系",{"key":22,"text":23,"correct":24},"D","横道图的工作可按项目对象排序",true,"通常横道图的表头为工作及其简要说明，项目进展表示在时间表格上，根据横道图使用者的要求，工作可按照时间先后、责任、项目对象、同类资源等进行排序。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]