[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117190":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117190,789,1,"单选题","编制控制性措施进度计划的主要目的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合理安排施工企业计划周期内的生产活动",false,{"key":16,"text":17,"correct":14},"B","具体指导建设工程施工",{"key":19,"text":20,"correct":14},"C","确定项目实施计划周期内的资金需求",{"key":22,"text":23,"correct":24},"D","对施工承包合同所规定的施工进度目标进行论证",true,"控制性施工进度计划编制的主要目的是通过计划的编制，以对施工承包合同所规定的施工进度目标进行再论证，并对进度目标进行分解，确定施工的总体部署，并确定为实现进度目标的里程碑事件的进度目标（或称其为控制节点的进度目标），作为进度控制的依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]