[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117188,789,1,"单选题","控制性施工进度计划的内容不包括（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","对承包合同的进度目标进行分析论证",false,{"key":16,"text":17,"correct":14},"B","确定施工的总体部署",{"key":19,"text":20,"correct":21},"C","划分各作业班组进度控制的责任",true,{"key":23,"text":24,"correct":14},"D","确定控制节点的进度目标","控制性施工进度计划编制的主要目的是通过计划的编制，以对施工承包合同所规定的施工进度目标进行再论证，并对进度目标进行分解，确定施工的总体部署，并确定为实现进度目标的里程碑事件的进度目标（或称其为控制节点的进度目标），作为进度控制的依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]