[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117187":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117187,789,1,"单选题","工程项目的施工总进度计划是属于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目的施工总进度方案",false,{"key":16,"text":17,"correct":14},"B","项目的指导性施工进度计划",{"key":19,"text":20,"correct":14},"C","项目施工的年度施工计划",{"key":22,"text":23,"correct":24},"D","项目的控制性施工进度计划",true,"一般而言，一个工程项目的施工总进度规划或施工总进度计划是工程项目的控制性施工进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]