[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117186":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117186,789,1,"单选题","在建设工程项目进度控制工作中，分析和论证进度目标的目的是分析和论证（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度目标的合理性及实现的可能性",true,{"key":16,"text":17,"correct":18},"B","进度目标实现措施的经济性和可操作性",false,{"key":20,"text":21,"correct":18},"C","进度目标与成本目标、质量目标的匹配性",{"key":23,"text":24,"correct":18},"D","进度目标与成本目标、质量目标的一致性","",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]