[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117184":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117184,789,1,"单选题","大型建设工程项目总进度目标论证的核心工作是通过（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制总进度纲要，论证总进度目标实现的可能性",true,{"key":16,"text":17,"correct":18},"B","分析工程发包组织方式，论证总进度目标分解的合理性",false,{"key":20,"text":21,"correct":18},"C","分析施工技术方面的资料，论证总进度目标的控制措施",{"key":23,"text":24,"correct":18},"D","分析施工组织资料论证总进度目标实现的条件","大型建设工程项目总进度目标论证的核心工作是通过编制总进度纲要论证总进度目标实现的可能性。总 进度纲要的主要内容包括： （1）项目实施的总体部署； （2）总进度规划； （3）各子系统进度规划； （4）确定里程碑事件的计划进度目标； （5）总进度目标实现的条件和应采取的措施等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]