[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117179":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117179,789,1,"单选题","建设工程项目的总进度目标是在项目的（ ）阶段确定的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","决策",true,{"key":16,"text":17,"correct":18},"B","设计",false,{"key":20,"text":21,"correct":18},"C","招标",{"key":23,"text":24,"correct":18},"D","施工","建设工程项目的总进度目标指的是整个项目的进度目标，它是在项目决策阶段项目定义时确定的。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]