[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117178":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117178,789,1,"单选题","在进行建设工程项目总进度目标控制前，首先应（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进行项目结构分析",false,{"key":16,"text":17,"correct":14},"B","确定项目的工作编码",{"key":19,"text":20,"correct":14},"C","编制各层进度计划",{"key":22,"text":23,"correct":24},"D","分析和论证目标实施的可能性",true,"在进行建设工程项目总进度目标控制前，首先应分析和论证目标实现的可能性。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]