[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117173":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117173,789,1,"单选题","分部分项工程成本分析采用的\"三算\"对比分析法，其\"三算\"对比指的是（）的比较。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","概算成本、预算成本、决算成本",false,{"key":16,"text":17,"correct":18},"B","预算成本、目标成本、实际成本",true,{"key":20,"text":21,"correct":14},"C","月度成本、季度成本、年度成本",{"key":23,"text":24,"correct":14},"D","预算成本、计划成本、目标成本","分部分项工程成本分析是施工项目成本分析的基础。分部分项工程成本分析的对象为已完成分部分项工程。分析的方法是：进行预算成本、目标成本和实际成本的“三算”对比。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]