[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117172":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117172,789,1,"单选题","某项目施工成本数据如下表，根据差额计算法，成本降低率提高对成本降低额的影响程度为（）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.6",false,{"key":16,"text":17,"correct":14},"B","0.7",{"key":19,"text":20,"correct":14},"C","1.1",{"key":22,"text":23,"correct":24},"D","1.2",true,"（3.5%-3%）×240=1.2 万元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]