[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117170,789,1,"单选题","施工项目年度成本分析的重点是（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","通过实际成本与目标成本的对比，分析目标成本落实情况",false,{"key":16,"text":17,"correct":14},"B","通过对技术组织措施执行效果的分析，寻求更加有效的节约途径",{"key":19,"text":20,"correct":14},"C","通过实际成本与计划成本的对比，分析成本降低水平",{"key":22,"text":23,"correct":24},"D","针对下一年度进展情况，制定切实可行的成本管理措施",true,"年度成本分析的依据是年度成本报表。年度成本分析的内容，除了月（季）度成本分析的六个方面以外，重点是针对下一年度的施工进展情况制定切实可行的成本管理措施，以保证施工项目成本目标的实现。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]