[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117169":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117169,789,1,"单选题","某分部工程的成本计划数据如下表所示，则第五周的施工成本计划值是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","75",false,{"key":16,"text":17,"correct":18},"B","155",true,{"key":20,"text":21,"correct":14},"C","80",{"key":23,"text":24,"correct":14},"D","125","本题考查的是施工成本计划的编制方法。根据图示计算，第5周的成本计划值为：30+45+80=155万元。参见教材P83。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]