[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117168":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117168,789,1,"单选题","某土方工程，计划总工程量为4800m3预算单价为580 元\u002Fm3，计划6 个月内均衡完成，开工后，实际单价为600 元\u002Fm3，施工至第3 个月底，累计实际完成工程量3000m3，若运用赢得值法分析，则至第3 个月底的费用偏差为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-34.8",false,{"key":16,"text":17,"correct":18},"B","-6",true,{"key":20,"text":21,"correct":14},"C","6",{"key":23,"text":24,"correct":14},"D","34.8","计算过程如下： 已完工作预算费用（BCWP）=已完成工作量×预算单价=3000×580=174（万元） 已完工作实际费用（ACWP）=已完成工作量×实际单价=3000×600=180（万元） 费用偏差（CV）=BCWP-ACWP=174-180=-6（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]