[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117162":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117162,789,1,"单选题","施工成本控制需要进行实际成本情况与施工成本计划的比较，其中实际成本情况是通过（）反映的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程变更文件",false,{"key":16,"text":17,"correct":18},"B","进度报告",true,{"key":20,"text":21,"correct":14},"C","施工组织设计",{"key":23,"text":24,"correct":14},"D","分包合同","进度报告提供了对应时间节点的工程实际完成量，工程成本实际支出情况等重要信息。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]