[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117158":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117158,789,1,"单选题","建设工程项目施工准备阶段的施工预算成本计划以项目实施方案为依据，采用（）编制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","人工定额",false,{"key":16,"text":17,"correct":14},"B","概算定额",{"key":19,"text":20,"correct":14},"C","预算定额",{"key":22,"text":23,"correct":24},"D","施工定额",true,"实施性计划成本即项目施工准备阶段的施工预算成本计划，采用企业的施工定额，通过施工预算的编制而形成的实施性施工成本计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]