[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117154":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117154,789,1,"单选题","某工程的赢得值曲线如下图，关于t1 时点成本和进度状态的说法，正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","费用节约、进度超前",false,{"key":16,"text":17,"correct":14},"B","费用超支、进度拖延",{"key":19,"text":20,"correct":14},"C","费用节约、进度拖延",{"key":22,"text":23,"correct":24},"D","费用超支、进度超前",true,"费用偏差=已完工作预算费用-已完工作实际费用 0，故进度超前。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]