[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117150":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117150,789,1,"单选题","建筑施工企业编制实施性成本计划时，宜以（）为依据。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工图预算成本",false,{"key":16,"text":17,"correct":14},"B","工程概算成本",{"key":19,"text":20,"correct":21},"C","施工预算成本",true,{"key":23,"text":24,"correct":14},"D","施工结算成本","施工成本计划按其作用可分为三类，即竞争性成本计划、指导性成本计划与实施性成本计划。竞争性成本计划是估算成本计划，以招标文件中的合同条件、投标者须知、技术规程、设计图纸或工程量清单等为依据；指导性成本计划是预算成本计划，以合同标书为依据；实施性成本计划是施工预算成本计划，以项目实施方案为依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]