[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117144":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117144,789,1,"单选题","根据建设工程项目施工成本的组成，属于直接成本的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工具用具使用费",false,{"key":16,"text":17,"correct":14},"B","职工教育经费",{"key":19,"text":20,"correct":21},"C","机械折旧费",true,{"key":23,"text":24,"correct":14},"D","管理人员工资","本题考查的是施工成本管理的任务。直接成本是指施工过程中耗费的构成工程实体或有助于工程实体形成的各项费用支出，是可以直接计入工程对象的费用，包括人工费、材料费和施工机具使用费等。选项C属于施工机具使用费。其他几个属于企业管理费",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]