[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117142":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117142,789,1,"单选题","施工成本分析是在（）的基础上，对成本的形成过程和影响因素进行分析。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工成本计划",false,{"key":16,"text":17,"correct":14},"B","施工成本预测",{"key":19,"text":20,"correct":21},"C","施工成本核算",true,{"key":23,"text":24,"correct":14},"D","施工成本考核","成本分析是在成本核算的基础上，对成本的形成过程和影响成本升降的因素进行分析，以寻求进一步降低成本的途径，包括有利偏差的挖掘和不利偏差的纠正。成本分析贯穿于成本管理的全过程，主要利用项目的成本核算资料（成本信息），与目标成本、预算成本以及类似项目的实际成本等进行比较，了解成本的变动情况。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]