[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117140":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117140,789,1,"单选题","项目经理部对竣工工程成本核算的目的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","考核项目管理绩效",true,{"key":16,"text":17,"correct":18},"B","寻求进一步降低成本的途径",false,{"key":20,"text":21,"correct":18},"C","考核企业经营效益",{"key":23,"text":24,"correct":18},"D","分析成本偏差的原因","对竣工工程的成本核算，应区分为竣工工程现场成本和竣工工程完全成本，分别由项目管理机构和企业财务部门进行核算分析，其目的在于分别考核项目管理绩效和企业经营效益。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]