[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117138":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117138,789,1,"单选题","在施工成本管理的各类措施中，一般不需增加费用，而且是其他各类措施的前提和保障的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","过程控制措施",false,{"key":16,"text":17,"correct":14},"B","经济措施",{"key":19,"text":20,"correct":14},"C","技术措施",{"key":22,"text":23,"correct":24},"D","组织措施",true,"组织措施是从施工成本管理的组织方面采取的措施。组织措施是其他各类措施的前提和保障，而且一般不需要增加什么费用，运用得当可以收到良好的效果。所",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]