[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117136":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117136,789,1,"单选题","按照我国现行规定，合同价款采用造价信息差额调整法调整时，当承包人投标报价中材料单价低于基准单价，施工期间材料单价涨幅以（）为基础超过合同约定的风险幅度值时，其超过部分按实调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基准单价",true,{"key":16,"text":17,"correct":18},"B","投标报价",false,{"key":20,"text":21,"correct":18},"C","市场价格",{"key":23,"text":24,"correct":18},"D","投标价和基准价的平均值","承包人投标报价中材料单价高于基准单价：施工期间材料单价跌幅以基准单价为基础超过合同约定的风险幅度值，或材料单价涨幅以投标报价为基础超过合同约定的风险幅度值时，其超过部分按实调整。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]