[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117130":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117130,789,1,"单选题","某建设工程由于业主临时设计变更导致停工，承包商的工人窝工8 个工日，窝工费为300 元\u002F工日；承包商租赁的挖土机窝工2 个台班，挖土机租赁费为1000 元\u002F台班，动力费160 元\u002F台班，承包商自有的自卸汽车窝工2 个台班，该汽车折旧费用400 元\u002F台班，动力费为200 元\u002F台班，则承包商可以向业主索赔的费用为（）元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5200",true,{"key":16,"text":17,"correct":18},"B","4800",false,{"key":20,"text":21,"correct":18},"C","5400",{"key":23,"text":24,"correct":18},"D","5800","可索赔的费用：人工费=300×8=2400元;租赁机械费=1000×2=2000元;自有机械费=400×2=800元。2400+2000+800=5200元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]