[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117129":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117129,789,1,"单选题","根据《建设工程工程量计价规范》，关于暂列金额的说法，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已签约合同中的暂列金额应由发包人掌握使用",true,{"key":16,"text":17,"correct":18},"B","已签约合同中的暂列金额应由承包人掌握使用",false,{"key":20,"text":21,"correct":18},"C","发包人按照合同规定将暂列金额作出支付后，剩余金额归承包人所有",{"key":23,"text":24,"correct":18},"D","发包人按照合同规定将暂列金额作出支付后，剩余金额由发包人和承包人共同所有","已签约合同价中的暂列金额由发包人掌握使用。发包人按照合同的规定支付后，如有剩余，则暂列金额余额归发包人所有。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]