[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117122":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117122,789,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），某工程签订了单价合同，在执行过程中，某分项工程原清单工程量1000m3，综合单价为25 元\u002Fm3，后因业主方原因实际工程量变更为1500m3，合同中约定，若实际工程量超过计划工程量15%以上，超过部分综合单价调整为原来的0.9，不考虑其他因素，则该分项工程的结算款应为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","36625",true,{"key":16,"text":17,"correct":18},"B","35000",false,{"key":20,"text":21,"correct":18},"C","33750",{"key":23,"text":24,"correct":18},"D","32875","该分项工程的结算款=1000m3×(1+15%)×25元／m3+[1500m3-1000m3×(1+15%)]×25元／m3×0．9=36625元。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]