[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117119":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117119,789,1,"单选题","某建设工程采用《建设工程工程量清单计价规范》。招标工程量清单中挖土方工程量为2500m3。投标人根据地质条件和施工方案计算的挖土方工程量4000m3，完成该土方分项工程的人、材、机费用为98000元，管理费13500 元，利润8000 元。如不考虑其他因素，投标人报计价时的挖土方综合单价为（）元\u002Fm3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","29.88",false,{"key":16,"text":17,"correct":18},"B","47.80",true,{"key":20,"text":21,"correct":14},"C","42.40",{"key":23,"text":24,"correct":14},"D","44.60","综合单价=(人、料、机费十管理费十利润)\u002F清单工程量=(98000+13500+8000)\u002F2500=47.80元\u002Fm3。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]